Home › Free guides › Interior & Alberta

Off-Grid Living in Interior BC, the Rockies and Alberta

Regions  12 min read

The BC Interior, the Rockies and Alberta share cold, dry winters, strong sun, heavy mountain snow in some valleys and a serious wildfire season almost everywhere. Rules change at the provincial border. This guide covers design temperatures and snow loads, the winter solar resource, foundation depth, BC and Alberta rules for wells, household water, septic systems, building permits and burning, land and access questions, wildfire and flood risk, and the system choices that suit the region.

Design climate

The BC values below are from Table C-2 of the 2018 BC Building Code. For Calgary the table gives the 99% heating design temperature and heating degree-days from the NOAA Engineering Weather Data record for 1973 to 1996, converted from Fahrenheit. The two sources use different statistics, so treat the Calgary row as a guide only and use the Alberta Building Code values for design.

LocationElevationJanuary design temperatureHeating degree-days (below 18 °C)Annual total precipitation
Kelowna, BC350 m−17 °C (1 °F)3,400325 mm (13 in)
Kamloops, BC355 m−23 °C (−9 °F)3,450275 mm (11 in)
Nelson, BC600 m−18 °C (0 °F)3,500700 mm (28 in)
Revelstoke, BC440 m−20 °C (−4 °F)4,000950 mm (37 in)
Cranbrook, BC910 m−26 °C (−15 °F)4,400400 mm (16 in)
Williams Lake, BC615 m−30 °C (−22 °F)4,400425 mm (17 in)
Golden, BC790 m−27 °C (−17 °F)4,750500 mm (20 in)
Prince George, BC580 m−32 °C (−26 °F)4,720600 mm (24 in)
Smithers, BC500 m−29 °C (−20 °F)5,040500 mm (20 in)
Fort St. John, BC685 m−35 °C (−31 °F)5,750475 mm (19 in)
Calgary, AB (NOAA, 99%)1,084 m−26 °C (−15 °F)about 5,180not given

The southern valleys are dry; Kamloops gets about a third of Victoria's precipitation. Northern and high sites are much colder. Fort St. John has more than one and a half times the heating degree-days of Kelowna, so the same house needs well over half again as much fuel there.

Worked example: the same house in three places

A house loses 150 W for every 1 °C of difference between inside and outside. Annual heat demand is the heat-loss rate × heating degree-days × 24 hours, the method set out in the wood heat guide.

  • Kelowna, 3,400 degree-days: 150 × 3,400 × 24 = 12,240,000 Wh, or 12,240 kWh.
  • Prince George, 4,720 degree-days: 150 × 4,720 × 24 = 16,990 kWh.
  • Fort St. John, 5,750 degree-days: 150 × 5,750 × 24 = 20,700 kWh.

The Fort St. John house needs 20,700 ÷ 12,240 = 1.69 times the heat of the Kelowna house. At the design temperature the gap is also large: 150 × (21 + 35) = 8,400 W at Fort St. John against 150 × (21 + 17) = 5,700 W at Kelowna, for a house kept at 21 °C.

Snow loads

Snow load is where this region varies most. The ground snow load Ss is the 1-in-50-year snow on the ground, in kilopascals; 1 kPa is about 102 kg per square metre (21 lb/sq ft). BC values are from the 2018 BC Building Code. Alberta values are the 2010 National Building Code figures as reproduced in a 2014 Boise Cascade specifier guide; current Alberta Building Code values may differ.

LocationSs (ground snow)Sr (rain on snow)
Kelowna, BC1.7 kPa0.1 kPa
Kamloops, BC1.8 kPa0.2 kPa
Prince George, BC3.4 kPa0.2 kPa
Nelson, BC4.2 kPa0.1 kPa
Golden, BC3.7 kPa0.2 kPa
Revelstoke, BC7.2 kPa0.1 kPa
Calgary, AB (NBC 2010)1.1 kPa0.1 kPa
Edmonton, AB (NBC 2010)1.7 kPa0.1 kPa
Grande Prairie, AB (NBC 2010)2.2 kPa0.1 kPa
Banff, AB (NBC 2010)3.6 kPa0.1 kPa

Worked example: one cabin, three valleys

A cabin roof covers 6 m × 8 m (19.7 ft × 26.2 ft), or 48 m² (517 sq ft). Design ground snow over that footprint, dividing kilonewtons by 9.81 to get tonnes:

  • Calgary, 1.1 kPa: 1.1 × 48 = 53 kN, about 5.4 tonnes.
  • Banff, 3.6 kPa: 3.6 × 48 = 173 kN, about 17.6 tonnes.
  • Revelstoke, 7.2 kPa: 7.2 × 48 = 346 kN, about 35.2 tonnes.

Revelstoke's design snow is more than six times Calgary's. The roof load the framing must carry comes from these ground values adjusted for slope, exposure and drifting by the designer. A steep metal roof sheds snow, but the sliding snow then piles against walls and over doors and must be planned for.

Foundations and frost

Frost goes deep in this region, and the code's minimum foundation depths depend on soil. Part 9 of the National Building Code and the BC Building Code (Table 9.12.2.2) require no minimum depth on rock, or on well-drained coarse sand and gravel. On clay or soils not clearly defined, the minimum is 1.2 m (3 ft 11 in), and for a building with no heated space the footings must also be below the depth of frost penetration. Silt under an unheated building also needs footings below frost depth.

The depth of frost penetration is set locally by the building authority. Ask for it before designing footings for an unheated cabin, shop or pump house, which are the buildings most often lifted by frost. Insulating a foundation to reduce heat loss to the soil under the footings means the code treats it as having no heated space.

Solar resource by month

The dry interior and the Alberta foothills get some of the clearest winter skies in Canada, but December days are still short. The table gives calculated day length and noon sun height on the 21st of each month at Calgary, 51.0° N. Kamloops and Cranbrook are within a few minutes of these figures. At Fort St. John, 56.2° N, the December day is about an hour shorter and the noon sun is 10° high.

Month (21st)Day lengthNoon sun height
January8.6 h19°
February10.3 h28°
March12.1 h39°
April14.1 h51°
May15.8 h59°
June16.6 h62°
July15.9 h59°
August14.2 h51°
September12.1 h39°
October10.2 h27°
November8.6 h19°
December7.9 h16°

Clouds are not included in these figures. A Natural Resources Canada study of rooftop solar potential found average yields across all roof surfaces of about 855 kWh per kW of panels per year in Kelowna and about 816 kWh/kW in Calgary, among the higher results of the 11 cities studied. Natural Resources Canada's photovoltaic potential maps give monthly values for over 3,500 municipalities and should be used for sizing.

Snow on the ground reflects sunlight onto panels, and cold panels produce more voltage than warm ones. Both help winter output in this region. Check that the string voltage at the coldest expected temperature stays within the charge controller's or inverter's maximum input voltage, since panel voltage rises as temperature falls. The solar power guide covers this calculation.

British Columbia rules

Water

Groundwater used only for a domestic purpose is exempt from licensing under the Water Sustainability Act. Domestic purpose covers household use, watering household animals and irrigating a garden of up to 1,000 m² next to the home. A domestic licence for surface water is optional, but gives a place in the "first in time, first in right" priority system. Unlicensed use of unrecorded surface water has no security of supply, which matters in the dry southern Interior where many creeks are fully licensed.

Septic systems

Systems designed for less than 22,700 L (5,000 imperial gal) per day that discharge to ground fall under the Sewerage System Regulation. They must be designed and installed by an authorized person: a registered onsite wastewater practitioner for Type 1 and Type 2 systems, or an authorized professional engineer, who may also do Type 3 systems. The authorized person files the system with the regional health authority and submits a letter of certification within 30 days of completing construction.

Building permits and owner-builders

Regional districts and municipalities issue building permits; some rural electoral areas have no inspection service. The Homeowner Protection Act applies everywhere: a new home must be built by a licensed residential builder with home warranty insurance, or by an owner who has passed an exam and holds an Owner Builder Authorization from BC Housing. An owner-built home can be sold only after it is complete and the owner has lived in it for at least one year, and a sale within 10 years needs an Owner Builder Disclosure Notice.

Open burning

A campfire is no larger than 0.5 m × 0.5 m. A Category 2 fire is one or two piles up to 2 m high and 3 m wide, or up to 0.2 ha of grass. Anything larger is Category 3. Smoke is regulated under the Open Burning Smoke Control Regulation, and burning depends on the day's Ventilation Index. Prohibitions on each category are common in summer. Report illegal fires on Crown land to 1-877-952-7277.

Alberta rules

Household water

Under Alberta's Water Act, a person who occupies land above groundwater or next to a water body, with no municipal water supply, may divert up to 1,250 m³ a year as a household user. Household use covers drinking, sanitation, fire prevention and watering animals, gardens, lawns and trees. Household users have the highest priority under the Act. A "traditional agricultural user" who diverted water before January 1, 1999 may continue to divert up to 6,250 m³ a year without a licence, but has priority protection only if the use was registered before 2003.

Worked example: is the household allowance enough?

1,250 m³ is 1,250,000 L. Spread over a year: 1,250,000 ÷ 365 = 3,425 L (905 US gal) per day.

A household of four using 100 L per person per day needs 400 L per day, about 12% of the allowance. A large summer garden or livestock can use much more. A drip-irrigated garden of 200 m² (2,150 sq ft) given 25 mm (1 in) of water a week uses 200 × 25 = 5,000 L a week, or about 714 L per day. Livestock or irrigation beyond the allowance need a licence.

Private sewage systems

Alberta's Private Sewage Disposal Systems Regulation adopts the Alberta Private Sewage Systems Standard of Practice 2021 for systems treating less than 25 m³ (5,500 imperial gal) a day. A permit is needed before installing, altering or adding to a system. Contractors must hold a certificate of competency to obtain permits. Some municipalities allow a homeowner living on the property to obtain a permit only for an open discharge system; check with the municipality or its safety codes agency. Permits also have time limits. In the County of Grande Prairie, for example, a private sewage permit expires if work does not start within 90 days of issue or stops for more than 120 days.

Safety codes permits

Building, electrical, gas, plumbing and private sewage work in Alberta all fall under the Safety Codes Act, and a permit is required before the work starts. In an accredited municipality, permits come through the municipality or its contracted inspection agency. In non-accredited areas, accredited agencies provide permits and inspections on the province's behalf, under the oversight of the Alberta Safety Codes Authority. Unlike some rural parts of BC, there is no part of the province where these permits are simply not required.

Fire permits

From March 1 to October 31, a fire permit is required for any burning in Alberta's Forest Protection Area. Campfires are exempt. Permits are free and are requested online through the province's fire permit system or from the local forest area office; an Alberta Wildfire representative replies within three business days, and a request is not approval to burn. Burning without a permit or outside its conditions can bring fines of up to $600. Fire bans can suspend permits. Outside the Forest Protection Area, the municipality sets the rules. Report a wildfire in a forested area to 310-FIRE (3473).

Wildfire and flood

Wildfire is the main hazard across this region. Many rural properties sit at the end of a single road through forest, so plan for evacuation as well as protection:

  • Use non-combustible roofing and siding, and screen vents and soffits with fine metal mesh.
  • Clear dry fuel, firewood and propane cylinders away from walls and decks.
  • Thin and limb conifers near buildings; keep grass short and green in summer.
  • Keep stored water, a gas-powered pump and hose for wetting down roofs and the ground around buildings.
  • Know two ways out if possible, and keep vehicles fuelled in fire season.

Heavy wildfire smoke can also cut solar output for days at a time in late summer. Keep enough battery capacity and generator fuel to ride through a smoky week.

Spring snowmelt floods rivers and creeks from April to June, and rain on a deep snowpack can raise them suddenly. Mountain creeks can also carry debris flows after wildfire has burned the slopes above them. Avoid building on alluvial fans and low benches next to creeks, and ask the local government for floodplain maps before buying.

Land and access

  • Agricultural Land Reserve (BC): much valley-bottom land in the Interior is in the reserve, where non-farm uses, extra dwellings and subdivision are restricted.
  • Crown land: in both provinces, building on or occupying Crown land requires a tenure.
  • Roads: resource roads may be gated, deactivated after logging or left unploughed in winter. Confirm year-round legal access and who maintains the road before buying.
  • First Nations land: reserve lands and treaty settlement lands have their own land rules. Confirm land status through the land title office and, where relevant, with the First Nation before planning any use.

Practical system choices

  • Heat: wood is the main heat source for most off-grid homes here, with propane or oil as backup. With 4,000 to 5,750 heating degree-days, plan for a large woodshed and a backup that can keep pipes from freezing while you are away. The wood heat guide covers cords per winter.
  • Batteries: keep them in a heated or insulated space. Check the manufacturer's minimum charging temperature; many batteries cannot be charged below freezing.
  • Solar: mount arrays steeply (55 to 70° from flat) so they shed snow and catch the low winter sun, and leave clear ground below for the snow to slide onto.
  • Water lines: bury them below the local frost depth, or run them inside an insulated, heat-traced chase. A pump house needs heat or must be drained in winter.
  • Propane: propane boils at about −42 °C (−44 °F). As it gets colder, tank pressure falls and a small tank cannot vaporize gas fast enough for a large appliance. In the coldest areas, use a larger tank than the load alone suggests, keep it full in winter, and do not rely on propane alone for freeze protection.
  • Generator: a generator with automatic start covers the December gap. Store fuel away from buildings in an approved container or tank.
  • Winter road access: a private road needs a plan for ploughing, a place to turn a vehicle around and room to pile snow. Keep emergency supplies in vehicles, since help can be hours away.
  • Snow management: plan where the roof snow will land, keep doors on gable ends, and budget for ploughing or a snowmobile if the road is not maintained.

Northern US equivalents

In northern Idaho, Montana and northeastern Washington, well permits, septic permits and burn permits come from state agencies and county health departments, and the rules differ from state to state. Mountain counties often set their own snow load values for building permits. Ask the county building department for the design snow load and frost depth before buying a house plan.

Key points

  • January design temperatures run from −17 °C at Kelowna to −35 °C at Fort St. John; heating degree-days from 3,400 to 5,750.
  • Ground snow loads range from about 1.1 kPa at Calgary to 7.2 kPa at Revelstoke. Use the code value for your site.
  • On clay or unknown soils, footings need at least 1.2 m of cover, and must be below frost depth under unheated buildings.
  • Winter skies are often clear but December days are under 8 hours. Mount panels steeply.
  • BC: domestic groundwater is licence-exempt; septic work needs an authorized person; new homes need a licensed builder or an Owner Builder Authorization.
  • Alberta: household users may divert 1,250 m³ a year; sewage, building, electrical, gas and plumbing work all need safety codes permits.
  • Fire permits are required in Alberta's Forest Protection Area from March 1 to October 31; BC regulates open fires by category. Prepare every property for wildfire.

This guide is general information. Codes, permits and safety requirements vary by province, state and municipality. Check local rules and use a qualified professional for electrical, gas, chimney and septic work where required.

The Comprehensive Off-Grid Manual

Every off-grid system in one manual, with worked examples, checklists and northern-climate detail.

Regions

Off-Grid Living on the Prairies

Prairie design cold, snow and wind loads, frost depth, solar by month, Saskatchewan and Manitoba septic and burning rules, dugouts, floods and systems.

12 min read